Tema–Aflao Coastal Highway Phase II

ActiveAshanti21 km · Urban11/11T00:00:00.000Z/202501/21T00:00:00.000Z/2027
Overall progress66%

Milestones

  1. 1
    Site MobilizationPaid
    Weight 10% · Due 04/30T00:00:00.000Z/2026
  2. 2
    EarthworksPaid
    Weight 20% · Due 06/14T00:00:00.000Z/2026
  3. 3
    Sub-base CoursePaid
    Weight 20% · Due 07/29T00:00:00.000Z/2026
  4. 4
    Asphalt Wearing CourseVerified
    Weight 25% · Due 09/12T00:00:00.000Z/2026
  5. 5
    Drainage & AncillaryPending
    Weight 15% · Due 10/27T00:00:00.000Z/2026
  6. 6
    Final HandoverPending
    Weight 10% · Due 12/11T00:00:00.000Z/2026