← Back to projects
Yendi–Saboba Trunk Road Reconstruction
ActiveAhafo31 km · Feeder08/03T00:00:00.000Z/2025 → 04/01T00:00:00.000Z/2027
Overall progress56%
Milestones
- 1Site MobilizationPaidWeight 10% · Due 04/30T00:00:00.000Z/2026
- 2EarthworksPaidWeight 20% · Due 06/14T00:00:00.000Z/2026
- 3Sub-base CoursePaidWeight 20% · Due 07/29T00:00:00.000Z/2026
- 4Asphalt Wearing CourseSubmittedWeight 25% · Due 09/12T00:00:00.000Z/2026
- 5Drainage & AncillaryPendingWeight 15% · Due 10/27T00:00:00.000Z/2026
- 6Final HandoverPendingWeight 10% · Due 12/11T00:00:00.000Z/2026